Preparation of Advanced Biological Wastewater Treatment Plant Application Projects
Scope of the project covers preparation of regional wastewater sectoral plan for the study are designs for approximately 100 km wastewater network and collector lines,50km creek rehabilitation, 1 pumping station, 2 wastewater preliminary treatment and 4 sea outfall and 6 advanced biological Wastewater Treatment Plants (WWTP) for population varying between 120 000-1.600.000.
WWTP flows:
Büyükçekmece WWTP Daily dry weather flow Qapprox: 581.851 m3/g
Çanta WWTP Daily dry weather flow Qapprox.: 222.609 m3/g
Tuzla WWTP Daily dry weather flow Qapprox: 200.000m3/g
Silivri WWTP Daily dry weather flow Qapprox: 172.236 m3/g
Riva WWTP Daily dry weather flow Qapprox: 35.000 m3/g
Kilyos WWTP Daily dry weather flow Qapprox: 30.000 m3/g